25kV/12kV Fuse and Switch Replacements — Kootenay Region, BC (2023)

Maple Leaf Power Corporation completed eight phases of 25kV/12kV fuse and switch replacements across the Kootenay region of BC in 2023, replacing approximately 1,500 fuse and switch components across overhead distribution systems. Individual phases ranged from 13 to 429 replacements. All phases were completed safely, on schedule, and to utility specifications.